A two-year-long sewer repair project in Montavilla is coming to an end. One of the last segments needing completion is near Montavilla Park, on Pacific Street, east of 82nd Ave. Work begins Monday and could continue for up to two months.
The Montavilla North and South Sewer Repair project started July 12, 2018. The project replaced or repaired miles of 100-year-old sewer pipe through a variety of construction techniques. Most of the work completed months ago. This work on Pacific Street and a few other small segments will complete the project.
Starting November 2, crews will use Cured-In-Place-Pipe lining (CIPP) and open trench construction on Pacific Street from 82nd Ave to 87th Ave. Portland’s Bureau of Environmental Services (BES) outlined the work planned for NE Pacific Street Sewer Repair on the project website.
NE Pacific Street between NE 82nd and NE 84th avenues – Beginning Monday, November 2, crews will begin repairing a mainline public sewer pipe using two construction methods, open trench and CIPP.
NE Pacific Street midway between NE 84th and NE 87th avenues – Beginning Monday, November 2, crews will begin repairing part of a mainline public sewer pipe using open trench construction method.