A large road project on SE 80th Ave has completed after six months of work. Crews replaced the existing road down to its base and filled in missing sidewalks. The project encompassed SE 80th Ave from SE Grant Street to SE Market Street. Additionally SE Mill Street, from SE 80th Avenue to SE 82nd Ave, was included in the project.

Last year these Montavilla roads were in bad shape. Not only were there few sidewalks, but the roadway had deteriorated. Trees had grown so large that only one direction of traffic could pass at a time. The road edge was ambiguous, making it dangerous for all modes of transportation in the area. That alone would be cause for concern but these roads are directly next to Bridger School. Being next to a school creates an excessive amount of pedestrian and bike traffic in the area.

Instead of cutting down the trees that made this road difficult, crews built around them. This tactic has widened the road substantially but preserved the existing natural character of this area.

The repaving and sidewalk infill project has connected SE 80th Ave from the PCC Campus to Burnside. It is safe to walk bike and drive the entire stretch. That was the goal of the Jade and Montavilla Multimodal Improvements Project and part of why such effort has been put towards SE 80th Ave.
Coverage of the construction phase of this project can be read in the Montavilla News article from February. Trips that had taken Montavilla residents along SE 82nd Ave, now can rely on SE 80th Ave as a safer alternative to busier streets.