NE Halsey Lane Reconfiguration Underway

On April 8th, road painting crews begin work to reconfigure NE Halsey Street between 68th and 81st Avenues. Truck-mounted equipment scrubbed the existing travel lane markings from asphalt while workers affixed temporary plastic reflectors to the removed paint’s location so drivers could continue to use the street. The Portland Bureau of Transportation (PBOT) expects the contractor to return within a few days to restripe the street in a new configuration. Drivers will lose one travel lane in each direction between NE 68th and 81st Avenues but gain a center turn lane, aiding in safer left turns. Cyclists will receive bike lanes on both sides of NE Halsey Street from NE 68th 81st Avenues.

Construction drawing of NE Halsey Street and 76th Ave, Illustrations courtesy PBOT

PBOT representative Hannah Schafer explained that their pavement marking contractor is waiting for dry weather to restripe the street. Earlier this year, project managers delayed work on a 70s Neighborhood Greenway-related improvement that will create protected crossings at NE 76th Avenue and Halsey Street. Two pedestrian refuge islands and a small raised concrete median on NE Halsey Street will reside in the center turn lane at this intersection. However, cement masons could not begin that work until crews created a center lane by reducing the travel lanes. Crossing improvement work can occur after the contractor completes the street marking work.

Crosswalk closed at NE 76th Avenue and Halsey Street, directing people to the two others that will have protective islands

Residents challenged by the current conditions on this dangerous roadway have advocated for improvements for nearly a decade. Its old four travel lane configuration drops to two lanes west of NE 71st Avenue and east of NE 81st Avenue, creating an odd section of greater vehicle capacity that induces speeding. Reduced travel lanes and better crossings are just some of the updates aimed at making this a safer stretch of road. A new mini roundabout, flashing beacons, and high visibility crosswalk markings will help people cross the street in this area with reduced worry that a driver will not see them.

NE 76th Avenue and Halsey Street crossing that will have a protective pedestrian island

Drivers on NE Halsey Street should expect construction delays as crews paint the asphalt over the next few days and workers begin constructing the in-road safety infrastructure. Pedestrians and cyclists should use extreme caution around incomplete safety improvements and note that traffic pattern changes could distract motorists.

Update: On April 11th, crews with Hicks Striping & Curbing returned to NE Halsey to paint the streets with a new lane configuration and add marked crossings at NE 76th Avenue.

Update: Soon after crews restriped the roadway, cement masons returned to install two pedestrian refuge islands and a small raised concrete median on NE Halsey Street at NE 76th Avenue.


Promotion: Help keep independent news accessible to the community. Montavilla News has a Patreon account or you can pay for a full year directly online. We invite those who can contribute to this local news source to consider becoming paid subscriber or sponsor. We will always remain free to read regardless of subscription.

NE Halsey Safety and Access Project

Construction crews will begin working on improvement projects along NE Halsey Street this summer. The Portland Bureau of Transportation (PBOT) will reshape the busy roadway from NE 69th to 92nd Avenues, reducing travel lanes to make room for bike infrastructure and creating nearly 1,500 feet of new sidewalk on the north side of the street between 85th and 92nd Avenues. Several enhanced pedestrian crossing points along the project path will increase safety, implementing a mini roundabout, flashing beacons, and high visibility crosswalk markings.

The summer 2024 work, currently in the planning phase, combines the efforts of the NE Halsey Street – Safety and Access to Transit Project with the 70s Neighborhood Greenway to improve conditions on the high-traffic street. Drivers will lose one travel lane in each direction between NE 68th and 81st Avenues but gain a center turn lane, aiding in safer left turns. Cyclists will receive bike lanes on both sides of NE Halsey Street from NE 68th 81st Avenues. Riders will transition onto two-way buffered bike lanes on the south side of NE Halsey Street between Jonesmore Street and 92nd Avenue.

Early PBOT lane reconfiguration cross section shows spacing. Note that the 5′ bike lanes are shown as 6′ wide in some more recent design documents

People trying to connect to NE Halsey Street from the NE 82nd Avenue MAX station will see improvements to the existing multiuse path between 81st and 82nd Avenues on the northern edge of Eastern Cathay‘s parking lot. Pedestrians crossing NE Halsey will gain new high-visibility crosswalks at NE 69th, 80th, and 84th Avenues. People crossing the faster-paced street at NE 88th Avenue can use the request button for Rectangular Rapid Flashing Beacons (RRFB), signaling drivers to yield. In addition to the new sidewalks, crews working for PBOT will reconstruct curb ramps to comply with the Americans with Disabilities Act (ADA). Many TriMet Line 77 bus stops along the project path will also see improvements.

2020 rendering of mini roundabout at 80th Ave. Image courtesy of PBOT

Funding for this project includes money for street lighting analysis with an option for additional lighting if needed. The Federal government provided $5,300,000 towards these enhancements. Developers paying Transportation System Development fees contributed $2,580,000 in funding. Because this project spans a Freeway overpass, the Oregon Department of Transportation’s Bridge Program supplied $412,120. Other Portland Bureau funding sources will provide the remaining project costs.

2020 rendering of Intersection at 68th Ave. Image courtesy of PBOT

Funds from the Greenway project will complete the construction of two pedestrian refuge islands and a small raised concrete median on NE Halsey Street. In September, cement masons finished reconstructing sidewalk corners and adding mid-block curb ramps for the 70s Greenway crossing at NE Halsey Street and 76th Avenue. PBOT paused that work last year until crews could remove the existing lane striping and repaint lines in a new configuration. Until that reconfiguration occurs, road crews cannot create the refuge island because it would block part of a travel lane.

Construction drawing of NE Halsey Street and 76th Ave, courtesy PBOT

Planning and funding for the NE Halsey Street improvements have taken years to come to fruition. Residents challenged by the current conditions on this dangerous roadway have advocated for this work for nearly a decade, and they should soon see the results of their work. Expect construction delays on NE Halsey Street this summer, but by the end of the year, people should begin to feel safer traveling through this section of Portland.


Promotion: Help keep independent news accessible to the community. Montavilla News has a Patreon account or you can pay for a full year directly online. We invite those who can contribute to this local news source to consider becoming paid subscriber or sponsor. We will always remain free to read regardless of subscription.

70s Greenway Crossings Progress and Delays

Last week, road crews continued construction on the NE Glisan Street crossing at 78th Avenue to support the 70s Neighborhood Greenway project. However, similar work on NE Halsey Street and 76th Avenue stalled due to a striping contractor’s mechanical difficulty. Other critical crossings on SE Stark and Washington Streets at 80th Avenue remain partially completed and unmarked.

Last week, drivers near NE Glisan Street and 78th Avenue experienced detours and lane closures as crews demolished several feet of the east side of a pedestrian refuge island. This work removed the remnants of a signal pole that had once supported Rectangular Rapid Flashing Beacons (RRFB). That signal pole and plastic delineator posts suffered repeated damage from vehicles driving over the island. The Portland Bureau of Transportation (PBOT) stopped replacing the island-mounted pole in 2021, relying on the RRFBs attached to utility poles on the road’s edge. For years, an orange traffic cone protected the exposed wires on the refuge island. This recent work on NE Glisan Street addresses the exposed wire issue, covering the electrical junction box and removing the pole anchoring bolts. Crews also installed pole-mounted signal request buttons for cyclists to activate without dismounting. Pedestrian refuge island reconstruction could include additional safety measures. However, design documents do not indicate a significant adjustment to the physical attributes of the pedestrian refuge island.

PBOT Provided design document for the NE Glisan Street crossing at NE 78th Avenue.

South of the active Greenway work, construction of two pedestrian refuge islands and a small raised concrete median on NE Halsey Street is likely delayed until next year. In September, cement masons completed reconstructing sidewalk corners and adding mid-block curb ramps for the 70s Greenway crossing at NE Halsey Street and 76th Avenue. Before work can begin on the in-street crossing elements, crews must remove the existing lane striping and repaint lines in a new configuration. NE Halsey will change from a four-lane design in this area to a three-lane street with bike lanes. This transformation will happen by reducing a travel lane in each direction and adding a center turn lane. Until that reconfiguration occurs, road crews cannot create the refuge island because it would block part of a travel lane. 

NE Halsey Street and 76th Ave

According to PBOT, the contracted painting company suffered equipment failure, which disrupted their busy schedule. That company, Hicks Striping & Curbing, is one of only two striping contractors in the northwest region approved to do this work. Specialized Pavement Marking is the other contractor and is equally busy. Consequentially, project planners anticipate delays in the Greenway crossing work. “We don’t anticipate striping this segment until spring 2024,” explained Hannah Schafer, Communications Director for PBOT. Construction schedules can shift on other projects, freeing up resources for this work, but for now, crews are waiting for updated pavement markings.

Construction drawing of NE Halsey Street and 76th Ave, courtesy PBOT

Other Greenway crossing projects in Montavilla are missing pavement markings, causing hardship for people using the intersections. SE Stark and Washington Streets at 80th Avenue recently received updates to support RRFBs. When the road crews repaved the work area, that work temporarily removed a high-visibility crosswalk on SE Stark Street. Without lane striping and marked crossings, pedestrians, cyclists, and drivers navigate with some ambiguity around conflict points in the street.

These are short-term challenges as the streets around the 70s Neighborhood Greenway project gain safety improvements. However, residents have demanded crossing improvements along these busy streets for years, and further delay is understandably disappointing. By next year, PBOT should complete the Greenway project, making way for other safety improvements in the area.

Update December 14th, 2023: Cement masons completed work on the NE Glisan Street crossing at 78th Avenue. It is now full functional for pedestrian users. PBOT should install the bike RRFB request buttons soon. As design documents indicated, crews did not install additional pedestrian refuge island safety enhancements. Work on the island removed the mounting bolts from the damaged RRFB signal pole and secured the wiring junction box with an access cover.


Promotion: Help keep independent news accessible to the community. Montavilla News has a Patreon account or you can pay directly online. We invite those who can contribute to this local news source to consider becoming paid subscribers or sponsors. We will always remain free to read regardless of subscription.

NE Halsey Crossing at 76th

This week, road crews began work on NE Halsey Street at 76th Avenue, reducing travel lanes to make room for two pedestrian refuge islands and buffered bike lanes. This intersection improvement work supports the 70s Neighborhood Greenway project, providing a safe north-south connector for people walking or rolling to their destination. NE Halsey’s lane reconfiguration will extend several blocks east and west from this crossing, creating one travel lane in each direction with a center turn lane. 

Construction drawing courtesy PBOT

NE Halsey is one of the city-identified high crash corridors, making an enhanced intersection necessary at this new greenway crossing. NE 76th Avenue shifts 90 feet off center at NE Halsey Street, creating two “T” intersections. Consequentially, engineers needed to construct extra in-road elements to protect multimodal cross traffic while allowing vehicle left turns. The new center turn lanes on NE Halsey will have two pedestrian refuge islands aligned with the east crossing of NE 76th Avenue and a short raised median to the west protecting a green striped bike crossing. Crews will reconstruct two corners featuring Americans with Disabilities Act (ADA) compliant ramps that align with mid-block curb ramps across NE Halsey Street. The SE corner of NE 76th Avenue and Halsey Street will also feature a westward curb extension, shortening the crossing distance and placing waiting pedestrians at the outer edge of the parking lane for greater visibility.

Illustration courtesy PBOT

The NE Halsey Street lane reconfiguration will extend from NE 70th to NE 80th Avenues and support other Portland Bureau of Transportation (PBOT) safety improvements planned for this busy street. Reducing the four vehicle travel lanes to two adds road width for painted bike lanes to protect cyclists and a center turn lane for added protection. “This three-lane configuration is a proven safety improvement that national studies and local experience show results in safer travel for everyone,” explained PBOT representative Dylan Rivera. As they approach this ten-block segment of NE Halsey Street, signage along the corridor will notify people that a traffic pattern change is coming up.

PBOT expects the project on NE Halsey Street to conclude later this year, with striping and signage added by the end of December 2023. During the next few months, crews will need to close some streets and crossings as well as reduce travel lanes. Cyclists and pedestrians should use caution around NE 76th Avenue and potentially find alternate routes. TriMet has temporarily closed bus stops serving the 77 line (Stop IDs 2453 & 2452) at NE 76th Avenue in both directions. Riders who use those boarding locations should plan for additional travel time to the next stop through September 17th for eastbound service and September 27th for westbound service.