The Portland Bureau of Transportation (PBOT) recently scaled back plans for the NE Halsey Street Safety and Access to Transit Project, postponing a planned intersection improvement at NE 69th Avenue and removing a 150-foot section of new sidewalk and street trees from the project’s scope. PBOT says the $380,000 in cost savings is necessary to meet reduced funding for this project while still maintaining core improvement goals of filling gaps in walking and biking connections on NE Halsey Street from NE 80th to NE 92nd Avenues.
In April, PBOT updated the “NE Halsey Street (68th to 92nd Avenues) – Safety and Access to Transit Project” website to redirect to the newly renamed “NE Halsey Street (80th to 92nd Avenues) – Safety and Access to Transit Project.” The removed western portion of the project cut a protected high-visibility crosswalk on NE Halsey Street at NE 69th Avenue and removed traffic flow improvements where Interstate 84 off-ramp traffic merges with NE 68th and NE 69th Avenues before joining a slip lane leading onto eastbound NE Halsey Street. This change pushes the start of bike lane infrastructure west of NE 70th Avenue and retains an intersection that some local residents have complained about for years. In 2020 outreach, it was identified as a conflict-heavy junction. In August 2025, PBOT representatives said the design would change, noting the 2020 rendering was outdated and no longer reflected current designs. Work on this portion of the project never broke ground.

PBOT spokesperson Dylan Rivera explained that the NE 69th Avenue segment is separated from the other project elements by several blocks, and a staff review determined that it was the only major element that planners could cut without compromising the overall safety designs of the other elements. He notes that street designers still consider this intersection a priority for future implementation. “The intersection design is fully complete. It’s a shovel-ready project,” remarked Rivera. “We believe it’s an important improvement, and we are actively pursuing funding to build it as originally planned. While the work will be delayed, it should not be considered canceled.”

The other project reduction is south of the new NE 81st and Halsey roundabout. This pedestrian connector would have created about 150 feet of sidewalk and street trees on the north side of NE 81st Avenue, where it curves towards NE Halsey Street. Pedestrians can still walk on the existing sidewalk across the street. The PBOT representative explained that the unbuilt section of the sidewalk would not have completely filled the sidewalk gap, leaving a 200-foot section where people would have to use the roadway or cross the street. However, the sidewalk segment would have connected to a shortcut path that leads to the 82nd Avenue Bus and MAX station. That path is currently closed due to safety concerns following the adjacent property owner’s fencing of their parking lot. It could reopen to the public at some point, and a sidewalk connection on NE 81st Avenue would be helpful, according to some transit users in the area.


PBOT says the cost savings implemented also shorten the project timeline by one month. Crews are nearing completion of the mini roundabout, which has taken months to construct. In December 2025, contractors began work on NE Halsey Street at NE 80th and NE 81st Avenues. At first, NE Halsey remained open to east-west through traffic as crews installed underground stormwater management pipes connecting to relocated catch basins as part of this street reconfiguration. The project then progressed to sidewalks and curbs on the south side of the intersection, with half the roundabout completed in early February. Starting February 16th, westbound motorists on NE Halsey Street began using a detour to NE 82nd Avenue during construction on the northern half of the new mini-roundabout. Crews completed paving in May, with the roadway still closed to vehicles at the time of publication.

The contractor working with PBOT on this project, Interlaken, and their subcontractors work the length of the NE Halsey job site. Rivera noted that observed inactivity at the roundabout was expected, as they manage resources across the whole project, and that Interlaken remains on track to finish work this summer. Pacific Power still needs to energize new power poles, and contractor Prairie Electric will install streetlights. Cement masons with Nu Wave Concrete have additional pavement work to complete around the intersection. PBOT expects the westbound Halsey closure to remain in place through the end of May to maintain crew safety working on the north side of the intersection.

PBOT has completed a new design for the postponed intersection improvements, which they anticipate will make it safer for people biking and walking to travel through the area where Interstate 84 eastbound travelers exit the highway and enter NE Halsey Street. Information about that work will likely become available when additional funding is secured by the transportation bureau.
Promotion: Check out East Portland News as it continues to advocate for and report on outer East Portland. You will find frequently updated articles and an archive of more than 5,000 stories written over the past 20+ years alongside a robust Community Calendar of events.
