This week, crews with the Portland Bureau of Transportation (PBOT) will continue road work that began on August 19 along NE Glisan Street between NE 82nd and NE 92nd avenues. Drivers in the area are encountering new traffic patterns and slower speeds as re-striping teams add painted bike lanes on completed segments of the project site and new signage arrives from NE 81st to NE 92nd Avenues. Workers have not restored all lane markings to the repaved half of the project site closest to NE 82nd Street. Road users should use extra caution until work is completed and anticipate delays during the 7 a.m. to 6 p.m., Monday through Thursday work schedule.

This Fixing Our Streets-funded project included substantial updates to sidewalk corner curb ramps, bringing crossings in this area up to Americans with Disabilities Act (ADA)- compliant standards. In addition to creating a smoother driving surface for vehicles, this new phase of work will reconfigure the street to remove time-shifting outer lanes used for parking or as an auxiliary travel lane. Collisions occurred on this street where motorists parked cars during allotted times, but drivers may have assumed the outer lane was clear. PBOT engineers anticipate that removing that conflict point will yield significant safety improvements with minimal impact on vehicle throughput.

In January 2021, crews posted new speed limit signs along NE Glisan Street east of 82nd Avenue, reducing top speeds from 35 mph to 30 mph. Then, in March 2024, PBOT lowered speed limits from 30 to 25 mph on NE Glisan Street between NE 57th and 82nd Avenues. Now, 25 mph speed limit signs have expanded eastward towards the Interstate 205 freeway. East- and west-traveling drivers will encounter new shared bike, bus, and right‑turn lanes as they approach NE 82nd Avenue.

The new NE Glisan bike lanes will connect NE 81st Avenue and NE 93rd Avenue. Early concepts for the cycling infrastructure showed the bike lane extending west to NE 80th. However, area business concerns over losing frequently used street parking on that block prompted a design that still helps connect side-street bike routes for people crossing NE 82nd Avenue outside a car, while minimizing impacts to adjacent commercial property users. PBOT planners anticipate further improving the bike infrastructure in 2030 with hardscape concrete dividers and flex posts to protect cyclists riding next to cars. The reconfiguration is happening during this repaving project to save money. Otherwise, contractors would need to grind off existing street markers and repaint as part of the 2030 work.

NE Glisan Street, from Interstate 205 to 82nd Avenue, is a notoriously challenging roadway to cross with vehicles driving quickly between the two points. Without any fully signalized intersections on this stretch and with a large hill blocking visibility, it can take an extended period to find a safe break in traffic to cross. Crews working with PBOT will install two new pedestrian crossings with concrete median islands at NE 84th and 90th avenues, along with enhancements to an existing crossing at NE 87th Avenue. These in-roadway waypoints allow pedestrians to cross in two phases, focusing on one direction of traffic at a time, and help drivers better see a person waiting at the high-visibility infrastructure.

In the coming days, crews will grind down the eastern segment of the roadway and lay a fresh road surface. Cyclists should consider safer routes until NE Glisan is fully re-striped, and all street users should plan extra travel time as people adjust to the new configuration and speed limits on this segment of NE Glisan.
Article and photos by
Promotion: Montavilla News is supported by contributions from businesses like Catalyst Construction & Kitchen Remodeling, a top-rated general contractor specializing in kitchen, bathroom, basement, and garage remodeling, as well as ADU construction and home additions. We thank them for their support.