Tag: SE Division

New Signal and Crossing at SE 80th and Division

Update – Crews recently installed the traffic signal mast-arm poles on the southern corners of SE 80th Avenue and SE Division Street. Soon workers will return to install the remaining two poles. Then city staff will place the new control box, signals, and LED street lights planned for this intersection. Within the next few months, this busy crossing will become available to pedestrians and cyclists who have struggled to use this space safely.


Update March 11th 2022 – Crews recently completed the south side curb ramps and sidewalk reconstruction at SE 80th and Division. Work has moved across the street to the north side of SE Division Street, spanning Portland Community College’s vehicle entrance. After concrete work completes, signal and painting specialists will add traffic control lights and new crosswalks to the intersection.

Southwest corner SE 80th and Division
Southeast corner SE 80th and Division

Original Article Published January 21st, 2022

Starting January 31st, crews with Raimore Construction will begin road work at the intersection of SE 80th Avenue and SE Division Street. This project adds traffic signals, marked crosswalks, and other safety measures for bikes and pedestrians. Work will continue through March, causing limited traffic delays in early February. This enhancement is part of the continuing Outer Division Safety Project between SE 80th to 174th avenues.

Portland Community College’s (PCC) southeast campus interrupts SE 80th Avenue at SE Division. The school’s parking lot entrance roughly aligns with the 80th along the college’s Division Street frontage. Currently, the intersection lacks signals, marked crosswalks, and ADA-compliant curb ramps.

PBOT bid document for SE 80th Ave and SE Division St with phase notes

Updates to this intersection will reconstruct all four street corners and provide gaps in the previously uninterrupted traffic flow. Crews will install new curb ramps, add high visibility crass-walk paint, and apply green-striped bike crossings where the SE Division bike lanes intersect 80th Avenue. This new crossing point creates additional connection opportunities to the 70s Neighborhood Greenway project scheduled to run through this area. Four signal poles will support eleven new traffic signals, providing aid to cyclists and pedestrians traversing the busy street. 

Around January 31st, crews will excavate a trench across SE 80th Avenue on the south side of SE Division Street. Cars turning onto SE 80th from Division Street or connecting with SE Division Street from 80th may experience lane closures. Between February 7th and 9th, trench work across SE Division at SE 80th will close down sections of SE Division street. However, traffic will be permitted in both directions during this work, with occasional lane diversions. Crews expect to close portions of PCC’s south parking lot entrance for a few days between February 10th and the 25th.

Pavement markings showing placement of new ADA curb ramps on southwest corner

Road flaggers will direct traffic during work hours, and plans strive for minimal impact on automotive traffic at the intersection. Work is scheduled between 7 AM and 3 PM, avoiding impact to the evening commute. In March, crews will install signal poles at the corners and complete other remaining work. This later construction should not affect vehicle traffic. However, pedestrians and bicycles may have minor detours.

Portland Bureau of Transportation engineers designed these infrastructure improvements to safely move all modes of travel through an increasingly active intersection. Commuters along SE Division have grown accustomed to this type of construction activity as the multi-year-long improvement project nears completion. When driving through this area, use caution and plan for additional travel time during work hours.

View from PCC parking lot south entrance looking across SE Division down SE 80th Ave

Affordable Housing at PCC SE Campus

At the end of 2021, Portland Community College (PCC) applied to the City of Portland for Early Assistance on a housing project located at 7705 SE Division Street. That process helps developers submit building permit applications that successfully meet City standards. The proposed development would construct approximately 100 affordable apartments within a single four-story building at a maximum height of 45′. Planners expect to provide around 30 surface parking spaces for the residents.

PCC acquired the property from the German American Society in May of 2010. Kaiser Permanente maintained a lease for the one-story building on the site until 2014. Midway through 2015, PCC began the process of demolishing the building and adding vehicle stalls to the existing parking lot. The area currently serves as auxiliary parking for the college and extended green space for the campus.

Image from Google Maps 2014

Last year, PCC staff worked to develop a twenty-year facilities plan for the educational institution’s properties. During that evaluation, PCC determined that portions of the school grounds should support low-income affordable housing. Instead of student-only dormitories, they opted to focus on attainable housing open to the public. From internal surveys of students, PCC staff learned that housing insecurity is a significant concern. They also observed that students often spread their education out over many years with inconsistent enrollment. Consequentially, PCC determined that tying housing programs to school affiliation would not help alleviate the housing insecurities among the student population. Instead, they feel creating more affordable housing inventory would provide better results.

Image from Google Maps 2015

Human Solutions and Bora Architects+Interiors are assisting PCC with early-stage planning. Efforts to design the building will begin next year. However, preliminary work masses the building towards SE Division Street with a green buffer zone along SE 77th Avenue. Designers are considering stepping down the building on SE Sherman Street to help blend in with the residential scale of that street. Apartments should range in size from studio units to three-bedroom family residences.

For the next twelve months, developers will continue to work with the community and design a housing project that serves residents, PCC, and the surrounding community. Final plans should materialize during the Summer of 2023, with construction following in Fall 2023. Interested community members should keep an eye out for future engagement opportunities.


Article cover image from Portland Maps

SE 82nd and Division Bus Stop Rebuild

Update – Crews have partially completed the bus stop reconstruction on SE Division Street at SE 82nd Avenue. Their progress reveals a design change for this station that will route bike riders behind the bus shelter instead of keeping bikes on the roadway. In this design, pedestrians will need to cross the raised bike lane to enter the bus platform.

Project documents from 2019 indicated that this location would implement a Pedestrian Bypass Station design, but work completed to date suggests workers are creating an Island Station. Consequently, crews are relocating the crosswalk signal currently in the middle of the future bicycle path. Despite this station’s changes, designers have maintained the sidewalk cutout to support replacement street trees near the bank building.

The final design will become apparent within the next few weeks as concrete work completes. As one of the last stations constructed in the Division Transit Project, it signals the imminent arrival of faster bus service. Look for TriMet FX™ (Frequent Express) service to begin in September 2022.


Original article published March 5th, 2022

This week, crews working on the Division Transit Project closed off traffic lanes on 82nd Avenue and SE Division Street as they demolished the intersection’s northwest corner. Workers removed two trees, a Trimet number 2 bus stop, and the drive-through exit driveway at Bank of the West. Soon TriMet will construct a new rapid bus station at this site and plant two new trees behind the bus shelter.

Bank of the West has two entry points to the financial institution’s parking lot, one on SE 82nd Avenue and another on SE Division Street. When the bank reworks their parking lot, drive-through ATM users will turn left, head back into the parking lot, and use either of the two remaining exits. Previously, users of the drive-through ATM could turn right and drive out onto Division through a third exit-only driveway. The longer articulated busses used in the Division Transit Project require more curbside space. Consequently, TriMet shifted the bus platform further west, blocking the drive-through exit path.

TriMet design plan for Division Transit Project. X marks removed trees and O indicates added trees.

This corner has ample sidewalk area, allowing TriMet to use its Pedestrian Bypass Station design. In that platform configuration, people walking past the stop have clear space to travel behind the waiting bus riders at the shelter. Additionally, this design allows bicyclists to ride past a parked bus in a separate lane to the left of the stop.

TriMet Pedestrian Bypass Station design

This latest TriMet work is one of the few reaming reconfigurations needed before the Division Transit Project begins service. Some limited use of the new bus stops will start in April, with full rapid bus service commencing later this year. A temporary number 2 bus stop is located less than 300 feet to the west form the construction site. Use cautions near this intersection and expect some delays over the next month.

2040 Portland Freight Plan

Portland Bureau of Transportation (PBOT) staff are in the midst of updating the City’s Freight Master Plan adopted by the Portland City Council in 2006. The 2040 Portland Freight Plan seeks to create a strategic road map for investing in urban freight infrastructure in Portland. This update allows the city to rebalance the commercial demands on the roads with the City’s Vision Zero and environmental goals. PBOT created a survey for Portlanders to help identify intersections, streets, curbs, bridges, ramps, and neighborhoods where people experience urban freight-related safety and mobility concerns.

Montavilla is a neighborhood surrounded and bisected by urban freight movement. The I84 and I205 freeways create its north and east borders, while 82nd Avenue, NE Glisan Street, SE Start/Washington Streets, and SE Division Street all carry substantial commercial traffic through the community. Businesses and residents in the neighborhood can provide unique perspectives to the survey, helping PBOT meet its goal of creating a safe, equitable, efficient, and sustainable urban freight system.

Participating in the PBOT survey is the public’s best opportunity to shape the next 20 years of freight activity in Portland. The results from the PBOT survey, along with extensive reports and analyses, will form the final Plan. Other guidance will come from the 2040Freight Community Advisory Committee (CAC) and Technical Advisory Committee (TAC) and multiple supporting documents developed throughout the planning process.


Title image courtesy of PBOT

The Barrier to Green Medians

SE Division Street is undergoing significant updates from 80th Ave towards 174th Ave. In addition to numerous safety enhancements, the Portland Bureau of Transportation (PBOT) will replace a continuous painted center turn-lane with a raised center median. Adding these dividers to busy streets provides substantial public benefit. They restrict left turn traffic to predictable places, protect crossing pedestrians, and provide space for added street trees. Perhaps more than the other benefits, community members enthusiastically awaited the expanded green spaces proposed for the center of this project. Unfortunately, PBOT is unable to provide most of the trees intended for SE Division Street.

Adding trees between multiple lanes of opposing traffic has several advantages. Visually it reduces the width of a road and can help reduce speeds by changing the character of a street. Additionally, generations of road designers have valued the sunshade and wind-breaking benefits that median trees provide. Consequential, PBOT staff intended to incorporate large numbers of trees into the Division Street redesign. However, decades of city infrastructure buried underground derailed plans to add them to the center of the road. “We originally planned on adding trees in all of the center medians coming to SE Division. However, during the design phase, we learned that the majority of proposed tree locations would be in conflict with an underground major water transmission line and also sewer infrastructure in certain areas.” Explained John Brady, Communications Director with PBOT.

Image courtesy of PBOT

PBOT will not forgo all center medians trees on SE Division. In total, crews will plant twenty new trees in the middle of the road at locations that do not conflict with underground utility lines. Montavilla will have a small cluster of trees between SE 84th and 85th Avenues. Crews will start construction on that segment of median in the coming weeks.

SE Division looking west towards 82nd Ave

Because PBOT cannot provide the expected number of trees in this project, Brady said they are shifting that portion of the work out to neighboring streets. “Since we are not able to plant as many trees as originally planned on SE Division, we will be working with the City’s Urban Forestry division to fund a planting project on adjacent side streets north and south of SE Division.” That project will add over 200 street trees within the public right-of-way. Tree planting work will occur in 2022 and 2023. Brady concedes that this is a compromise to PBOT’s original vision. “We recognize this won’t have the same effect as adding trees directly on SE Division Street, but it will help with overall air quality, stormwater management, and combating the heat sink in this part of East Portland.”

The twenty new street trees on SE Division will not be alone forever. As properties redevelop along the roadway, the City will require the construction of wider sidewalks with street trees. This approach will take decades to achieve the same green-scape initially imagined for the busy street’s renovation. However, it is the best option available at the moment. Perhaps as City engineers plan new utility line projects, they will consider shifting infrastructure away from the center, allowing for future planting of greenery between the vast expanses of pavement.

PCC’s Draft Twenty Year Facilities Plan

This week, Portland Community College (PCC) released the latest draft of its district-wide Facilities Plan. The proposal covers all four PCC campuses, including the Montavilla location at the northwest corner of SE Division Street and 82nd Avenue. Details are available at the Facilities Planning Online Open House website until October 22nd.

The current Southeast Campus opened 20 years ago in a repurposed grocery store at 2305 SE 82nd Ave. Infrastructure investments over the years have expanded the campus to include new education-focused buildings. However, as the student population increases, there is a need to replace outdated facilities and construct new spaces. PCC leadership believes they can efficiently accommodate the next two decades of growth by developing a comprehensive expansion plan. The second phase of that work is concluding at the end of this year.

Over the last year, PCC representatives collected feedback from students, faculty, staff, and PCC neighbors about the physical environment at each campus. The researchers combined this qualitative input with data on student enrollment, regional demographics, and market trends to create development concepts that accommodate the next 10 to 20 years of college growth.

The Open House presentation outlines five primary developments recommended for the Southeast Campus. PCC intends to add a new wing to Mt.Scott Hall along SE 82nd Ave. The former single-story grocery store building, designated as Mt. Tabor Hall, will be replaced with a more efficient three-story structure featuring a greater connection to public spaces. PCC would build a new gym and childcare facility roughly located on the land currently housing the Community Hall Annex building. This new building will extend the active campus further west. The large parking lot spanning PCC’s portion of SE 77th Ave could become the location for affordable housing.

Additionally, planners are considering an expansion of the campus by acquiring the land currently owned by Bank of the West at 8135 SE Division Street. The bank’s 9,888 square foot property could become the primary entrance to campus, reinforcing PCC’s goal of using campus edges to connect with the community.

The space between buildings received as much attention within the proposal as the structures themselves. Planners prioritized peaceful outdoor areas in the campus core, providing an antidote to the commotion caused by the school’s location at an intersection of two busy streets. The proposal includes safe and interconnecting pathways that traverse flexible-use green spaces while connecting the neighborhood through the campus.

The facilities planning review process is nearing completion. A short survey accompanies the Facilities Planning Online Open House presentation. Neighbors should review draft concepts for each PCC campus and provide comments before the October 22nd deadline. Answers to these last questions will further refine the plan ahead of its completion. The finalized Facilities Plan will be publicly available in December.


Correction: A previous version of this article stated that Southeast Campus opened 40 years ago in its current location. The campus relocated to this space 20 years ago after existing at another site for 20 years before that move.

SE Division Turn-Lane Reconfigured

This month, construction crews began lane reconfiguration work on SE Division Street near SE 92nd Ave. The Portland Bureau of Transportation (PBOT) will replace a continuous painted center turn-lane with physical separation and left turn controls. Portions of the center divider will transform into a raised median with street trees and pedestrian islands. This work is part of the Outer Division Safety Project and the Division Transit Project.

Out past 82nd Ave, SE Division Street features five lanes dedicated to automobiles traffic. Two lanes accommodate vehicles traveling westbound, and two are for eastbound traffic. The fifth lane is a multi-directional turn-lane used for short distances while executing a turn. PBOT determined that a significant number of crashes occurred to vehicles using the turn-lane. By adding a raised center median to SE Division, PBOT expects to reduce collisions between cars and produce safer pedestrian crosswalks.

Example of marked left turn space. Image courtesy of PBOT

Creating a raised median will change how drivers access businesses and side streets. The continuous divider will restrict left turns along the road except for designated areas. Drivers needing to access a location on the left side of the road may need to drive past their destination and execute a U-Turn at a marked left turn space. This configuration confines cross-traffic to specific locations and eliminates head-on collisions by cars using the turn-lane simultaneously.

Image courtesy of TriMet

Non-motorists will also benefit from the raised median. A lane-width divider will provide a mid-crossing island for pedestrians to safely wait for cars to stop. This protective space allows two shorter crossings and reduces the length of time both directions of traffic need to stop when yielding to foot traffic. Additionally, bicycle commuters will be less vulnerable to unexpected cross-traffic with the new configuration. The raised median does not resolve all bicycle collision issues. However, it will reduce those interactions to marked intersections where there should be better visibility.

Work on SE Division will continue until the Summer of 2022. Look for disruptions to normal traffic flow over the coming months as crews install the permeant median. Drivers and pedestrians should use extra caution in this area as people adjust to the new configuration.

PCC’s Twenty Year Facilities Plan

Today Portland Community College (PCC) launched a survey seeking input from students, staff, faculty, and the community regarding the college’s four campuses. The survey results, coupled with feedback received from online workshops, will help shape the facilities plan, guiding the future investment and priorities over the next ten to twenty years.

James Hill, the PCC Public Relations Manager, explained that they are interested in hearing from all people who interact with the campus, including neighbors. “In addition to ensuring the physical space supports the communities we serve, we are also interested in input to help PCC provide a more welcoming and inclusive place to learn, teach, work, and visit.”

The online Visioning Workshop for Montavilla’s Southeast Campus is scheduled for Thursday, April 22. It begins at 9:00 AM and runs through 10:30 AM. You can Register on Zoom for the meeting. However, Hill encourages residents of the neighborhood to participate via the online survey, which is available at the project website www.pcc.edu/fp2. Questions will ask for priorities regarding buildings and the outdoor areas with a focus on increased accessibility.

When all the data is collected, PCC will share the results via the project website, providing a summary of what they gathered at the campus workshops and through the survey. Participant’s input will inform the planning team while they draft recommendations for future development at each campus. Later this year, PCC will seek community input again on draft recommendations and ideas through another online survey. The team will refine the proposed plans based on community input and publish a final report at the end of 2021.

New Division Bus Station at 85th

Concrete work is complete on the new bus platform along SE Division Street, east of 85th Ave. It is one of several enhanced bus stations designed for faster public transportation between the outer Southeast and Downtown. TriMet’s Division Transit Project is underway at many points along the busy street, creating new infrastructure improvements. 

Image courtesy TriMet

Over the next year, upgrades to bus stops along this route will facilitate faster passenger loading and reduced bus merging times. This station’s platform design features a raised curb for better floor alignment with new longer buses. The platform’s curb extends out from the sidewalk through the bike lane to meet the travel lane. This design allows the bus to stop in traffic, eliminating the need to merge when the vehicle begins moving again. Integrated ramps on both edges of the platform allow bikes to pass through the bus stop. Bicyclists will briefly ride at sidewalk level to pass over the platform. However, to avoid collisions with TriMet riders, bikes will yield to pedestrians while buses load passengers.

Image courtesy TriMet

Some property owners at this location had expressed concern over the new platform design. Construction at this location removed a driveway that once provided off-street parking from the property at 8525 SE Division Street. Despite the removal of the curb-cut, the property still maintains two access points on SE Division Street. TriMet representative Roberta Altstadt explained that this “project will not completely eliminate any property’s access to a public right of way.” General community benefits brought by this work outweigh sidewalk reconfiguration concerns. This project not only improves transit but also rebuilds large sections of sidewalk and street corners.

One of two remaining driveways for 8525 SE Division Street

The Division Transit Project will complete in 2022. Although a year away from full use, SE Division Street improvements are already apparent, providing this worn roadway a needed refresh. Transit projects at this scale can attract further development to the area and draw in more commerce. Look for continued construction along SE Division Street over the next eighteen months.

View from the bike lane

Enchilada Express Opens on Division

Enchilada Express opened its second location this week. The new restaurant, serving Mexican food, is open for takeout. Located on SE Division next to the recently completed Pacific Plaza, this additional location is in the heart of a rapidly growing section of Montavilla.

Located at 8245 SE Division Street, this Enchilada Express location joins the original restaurant on SE Powell Blvd. The menu offers a range of Mexican dishes that should be popular with the lunchtime crowd. Place orders over the phone at 503-477-9800, on their website, or when visiting the location.